LocationWhite Plains, Charles County, Maryland
MarketPump Stations
TEMPORARY PUMP-AROUND SYSTEM, PRECAST WET WELL, SUBMERSIBLE PUMPS, FORCE MAIN, CONTROLS, TEMPORARY ELECTRICAL SERVICE, GENERATOR, ACCESS ROAD, AND FINAL SYSTEM REMOVAL.
Johnston Construction Company
- Johnston Construction Company furnished and installed a complete temporary pump-around system supporting construction and commissioning of Stonehaven Neighborhood Pumping Station No. 8.
- JCC installed an eight-foot-diameter precast-concrete temporary wet well with watertight, bolt-down H-20 access hatches, manhole steps, ventilation, and an epoxy-coated interior.
- The temporary station included duplex submersible solids-handling pumps, interior piping, valves, controls, alarms, and associated operating accessories.
- JCC installed temporary influent and discharge piping, including the force-main piping, fittings, bends, valves, and connection provisions required to transfer wastewater around the permanent station work.
- Electrical construction included temporary service, approximately 300 feet of conduit and trenching, power and control wiring, grounding, a duplex control panel, cellular autodialer, battery backup, automatic transfer switch, and standby generator.