LocationElkton, Cecil County, Maryland
MarketWater Storage and Tanks
TANK FOUNDATION, SITE PREPARATION, SURVEYING, UNDERGROUND WATER MAIN, TANK DRAIN, PROCESS PIPING, VALVES, VAULTS, CONCRETE FLOOR, ELECTRICAL SERVICE, DUCTBANKS, LIGHTING, GROUNDING, INSTRUMENTATION, TESTING, AND PROJECT CLOSEOUT.
Johnston Construction Company
- Johnston Construction Company completed the civil, mechanical, electrical, and instrumentation work associated with the Southfields Elevated Water Storage Tank project in Elkton, Maryland.
- JCC’s work supported construction of a new 600,000-gallon elevated water storage tank for the Town of Elkton.
- The project included site layout, surveying, utility coordination, preliminary site preparation, tank-foundation excavation, structural backfill, reinforced-concrete foundation construction, and installation of CB&I-furnished anchor bolts.
- JCC prepared the site for tank construction, including installation of the crane-access road, stone working area, crane pad, and hoist deadman required for tank erection.
- The civil scope included installation of valves, fittings, vaults, manholes, approximately 12-inch water-main piping, and an 8-inch tank-drain system.
Concrete Services Division
- Concrete Services Division, LLC completed the concrete work associated with the Southfields 600,000-Gallon Elevated Water Storage Tank project in Elkton, Maryland.
- CSD furnished the labor, form materials, tools, finishing supplies, curing materials, concrete accessories, and reinforcing-steel placement labor required for its assigned work.
- The project included concrete construction for the elevated water-storage-tank foundation, splash pad, pipe pads, and associated structural features.
- CSD completed slab-on-grade and curved-wall formwork required for the tank-foundation construction.
- The work included concrete placement, floating, screeding, machine troweling, pointing, patching, curing, accessory installation, reinforcing-steel placement, dowel installation, and pipe-pad construction.
Electrical Services Division
- Electrical Services Division, LLC completed the electrical work associated with the Southfields Elevated Water Storage Tank project in Elkton, Maryland.
- ESD furnished the labor, materials, tools, equipment, and supervision required to construct the electrical systems serving the new 600,000-gallon elevated water storage tank.
- The work included electrical ductbank excavation, underground conduit, power and control wiring, boxes, devices, electrical equipment supports, and final equipment connections.
- ESD furnished and installed the electrical-distribution equipment, including a transformer, lighting panel, circuit breakers, disconnecting equipment, and surge-protection equipment.
- The project included interior and exterior LED lighting, switches, receptacles, emergency lighting, and associated raceways and wiring.