LocationLewes, Sussex County, Delaware
MarketWater Storage and Tanks
CIVIL, FOUNDATION, MECHANICAL, ELECTRICAL, AND INSTRUMENTATION WORK FOR A NEW 1,000,000-GALLON ELEVATED WATER-STORAGE TANK.
Johnston Construction Company
- Johnston Construction Company performed the civil, foundation, mechanical, electrical, and instrumentation construction supporting a new one-million-gallon elevated water-storage tank for Tidewater Utilities.
- JCC constructed the reinforced-concrete tank foundation and coordinated the foundation geometry, pile system, anchor locations, embedded components, and interfaces with CB&I’s tank design.
- The foundation work included pile installation, pile testing, excavation, dewatering where required, spoil removal, concrete construction, backfill, compaction, and restoration.
- JCC completed site preparation, grading, erosion and sediment controls, drainage improvements, temporary access, and final restoration of the affected project areas.
- The work included installation of the water-main piping, valves, fittings, tank overflow piping, splash pad, storm drainage piping, and related site piping required for the completed facility.
Concrete Services Division
- Concrete Services Division, LLC performed the concrete construction supporting the new one-million-gallon South Rehoboth District elevated water-storage tank.
- CSD formed and placed the reinforced-concrete tank foundation in accordance with the project documents and CB&I foundation drawings.
- The work included the tank floor slab, curved foundation walls, splash pad, pipe-support pads, door pad, sump pit, and associated concrete elements.
- CSD installed footing, slab-on-grade, and curved-wall formwork and completed the required form stripping after the concrete achieved sufficient strength.
- The company coordinated the placement of approximately 116 cubic yards of concrete purchased by Johnston Construction Company.
Electrical Services Division
- Electrical Services Division, LLC performed the electrical construction supporting the new one-million-gallon South Rehoboth District elevated water-storage tank.
- ESD furnished and installed conduit, conductors, boxes, devices, switches, receptacles, and electrical connections throughout the tank site.
- The work included a new electrical rack, utility-meter provisions, main disconnect, lighting panel, and surge-protection equipment.
- ESD installed lighting fixtures serving the elevated tank structure and associated operational and maintenance areas.
- The project included underground duct bank, conduit, grounding, and conductors serving the site gate operators.