LocationMilton, Sussex County, Delaware
MarketWater Treatment Plants
GENERAL CIVIL SITE CONSTRUCTION, RAW-WATER AND FINISHED-WATER PIPING, WATER-MAIN CONNECTIONS, CHEMICAL STORAGE AND FEED SYSTEMS, FLUORIDE SATURATOR, MECHANICAL AND PLUMBING SYSTEMS, VENTILATION, SANITARY SEWER, DRIVEWAY IMPROVEMENTS.
Johnston Construction Company
- Johnston Construction Company served as the prime General Contractor for Contract 2020-0131 of the Shipbuilders Well & Water Treatment Facility project.
- JCC coordinated its general construction work with the separate architectural and electrical prime contractors responsible for the treatment-building construction and electrical systems.
- The company completed general civil site construction, including clearing, excavation, grading, backfill, erosion and sediment controls, driveway improvements, and restoration.
- JCC installed approximately 205 linear feet of six-inch PVC sanitary-sewer service between the new water-treatment building and the existing sanitary-sewer system.
- The company installed approximately 40 linear feet of six-inch PVC raw-water main between the well and the treatment building.