LocationMillville, Sussex County, Delaware
MarketWater Storage and Tanks
CIVIL, FOUNDATION, MECHANICAL, ELECTRICAL, AND INSTRUMENTATION WORK FOR A NEW 1,000,000-GALLON ELEVATED WATER-STORAGE TANK.
Johnston Construction Company
- Johnston Construction Company performed the civil, foundation, mechanical, electrical, and instrumentation construction supporting a new one-million-gallon elevated water-storage tank.
- JCC constructed the pile-supported reinforced-concrete foundation required for the new pedestal spheroid tank.
- The work included site preparation, excavation, dewatering where required, foundation backfill, compaction, grading, erosion and sediment controls, and final restoration.
- JCC installed approximately 1,175 linear feet of 20-inch water main, three 20-inch gate valves, a fire-hydrant assembly, and a two-inch blowoff assembly.
- The project included tank-overflow piping, a splash pad, storm-drainage piping, the site entrance, and supporting site improvements.
Concrete Services Division
- Concrete Services Division, LLC performed the concrete construction supporting the new one-million-gallon Ocean View District elevated water-storage tank.
- CSD formed and placed the reinforced-concrete tank foundation in accordance with the contract documents and CB&I foundation drawings.
- The concrete scope included the tank floor slab, curved foundation walls, splash pad, pipe-support pads, door pad, sump pit, and related structural concrete.
- CSD installed footing, slab-on-grade, and curved-wall formwork and completed form stripping after the concrete achieved sufficient strength.
- The company coordinated the placement of approximately 115 cubic yards of concrete purchased by Johnston Construction Company.
Electrical Services Division
- Electrical Services Division, LLC performed the electrical construction supporting the new one-million-gallon Ocean View District elevated water-storage tank.
- ESD furnished and installed conduit, conductors, electrical connections, boxes, switches, receptacles, and supporting devices throughout the tank site.
- The work included an electrical rack, utility-meter provisions, main disconnect, lighting panel, and transient-voltage surge-suppression equipment.
- ESD furnished and installed the interior and exterior lighting systems serving the elevated tank and its operational areas.
- The lighting package included seven Type A fixtures, one Type B fixture, two Type C fixtures, and a flight light.