Markets Served / Project Experience

Ocean City 28th Street Wastewater Pumping Station Improvements

Ocean City, Worcester County, Maryland

LocationOcean City, Worcester County, Maryland
MarketPump Stations

PUMPING STATION, MECHANICAL, ELECTRICAL, STRUCTURAL, BYPASS, AND SITE IMPROVEMENTS.

Johnston Construction Company

  • Johnston Construction Company completed the 28th Street Wastewater Pumping Station Improvements project for the Town of Ocean City, Maryland.
  • The project included wastewater pumping station improvements, mechanical and electrical equipment, support systems, appurtenances, site work, structural improvements, and related miscellaneous work.
  • JCC’s scope included construction coordination, demolition, earthwork, excavation, trenching, backfilling, pavement restoration, outside piping, grading, structural improvements, pumping equipment, mechanical systems, electrical systems, instrumentation, controls, bypass operations, startup, testing, and closeout.
  • Major equipment and systems included submersible chopper pumps, davit crane, packaged engine generator, automatic transfer switch, surge protective devices, motor starters and relays, panelboards, lighting, instrumentation, control systems hardware, heating and ventilation equipment, ductwork, piping, valves, and fittings.
  • The work required careful sequencing at an existing wastewater pumping station to maintain operations, protect existing utilities, coordinate bypass pumping, complete electrical and control integration, and return the station to service.

Concrete Services Division

  • Concrete Services Division, LLC performed concrete forming and concrete placement work for the 28th Street Wastewater Pumping Station Improvements project in Ocean City, Maryland.
  • The project included concrete support for wastewater pumping station improvements, including structural improvements, equipment support systems, pump station appurtenances, and related site improvements.
  • CSD’s scope included concrete forming, concrete placement, finishing, curing, concrete accessories, reinforcing steel support, patching, anchor bolts, sleeves, embeds, and related concrete coordination.
  • Major concrete work included the pumping station building footing, wall, slab, and equipment pad.
  • CSD performed concrete work for stairs, including stair footing, landing, steps, and related forming and placement.