Northeast Tank Altitude Valve Vault

Aberdeen, Harford County, Maryland

LocationAberdeen, Harford County, Maryland
MarketWater Storage and Tanks

ALTITUDE-CONTROL VALVE, PRECAST CONCRETE VAULT, DUCTILE-IRON PIPING, VALVES, ELECTRICAL POWER, TELEMETRY, INSTRUMENTATION, HEATING, VENTILATION, DEHUMIDIFICATION, EXCAVATION, BACKFILL, PAVEMENT RESTORATION, TESTING, DISINFECTION.

Johnston Construction Company

  • Johnston Construction Company served as the prime General Contractor for construction of the Northeast Tank Altitude Valve Vault.
  • JCC installed a new altitude-control valve and associated water piping to regulate the operating level of the City’s Northeast water-storage tank.
  • The company furnished and installed a new precast-concrete utility vault complete with access hatch, ladder, manhole components, pipe penetrations, seals, and supporting appurtenances.
  • JCC completed excavation, test pits, shoring, dewatering, bedding, aggregate placement, structural backfill, compaction, grading, and restoration required for the underground vault.
  • The company installed ductile-iron piping, fittings, flanged and mechanical joints, restraints, supports, anchors, couplings, and isolation valves.

Electrical Services Division

  • Electrical Services Division performed the electrical construction supporting the City of Aberdeen’s new Northeast Tank Altitude Valve Vault.
  • ESD demolished the existing lighting panel and removed electrical components that conflicted with the new installation.
  • The company furnished and installed conduit, conductors, boxes, devices, electrical connections, supports, and associated materials throughout the valve-vault facility.
  • ESD furnished and installed the new lighting fixtures, switches, and receptacles required for safe operation and maintenance of the underground vault.
  • The company furnished and installed the fan disconnect, electrical panelboard, and surge-protection device.

Browse all project experience