CIVIL, MECHANICAL, ELECTRICAL, AND INSTRUMENTATION CONSTRUCTION FOR NEW 2,000,000-GALLON COMPOSITE ELEVATED WATER STORAGE TANK.

Johnston Construction Company

  • Johnston Construction Company performed civil, mechanical, electrical, and instrumentation work for the Industrial Zone Water Storage Tank in Berkeley County, West Virginia.
  • The project included construction of a new 2,000,000-gallon composite elevated water storage tank consisting of a concrete pedestal and steel cylindrical bowl.
  • JCC’s scope supported the Industrial Zone tank near Development Drive, including site work, watermain installation, mechanical piping, valves, electrical and instrumentation systems, tank foundation coordination, testing, documentation, and closeout support.
  • Major work included site preparation, erosion and sediment controls, excavation, dewatering, on-site watermain installation, stormwater management piping, infiltration trench installation, valve installation, electrical service coordination, electrical and instrumentation work, lighting, grounding, testing, disinfection, record drawings, O&M manuals, and final grading and restoration.
  • The Industrial Zone tank included approximately 500 linear feet of on-site watermain ranging from 16-inch to 20-inch nominal diameter, check valves, gate valves, butterfly valves, altitude valves, stormwater management piping, infiltration trench, and related appurtenances.

Concrete Services Division

  • Concrete Services Division, LLC performed concrete forming, placement, finishing, curing, and accessory work for the Industrial Zone 2MGAL Elevated Water Storage Tank in Martinsburg, West Virginia.
  • The project included construction of a new 2,000,000-gallon composite elevated water storage tank as part of the Industrial Zone and Ridge Road Water Storage Tanks project for Berkeley County Public Service Water District.
  • CSD’s scope included concrete work for the tank foundation, including slab-on-grade forming, curved wall forming, straight wall forming, bulkhead forming, slab-on-grade placement, wall placement, grout placement, float and screed work, trowel finishing, point and patch work, curing, concrete accessories, and pipe pads.
  • Major work included mobilization and demobilization of concrete equipment, tools, and supplies; rental of form material; purchase of form lumber; installation and stripping of forms; concrete placement labor; concrete finishing labor and supplies; concrete curing labor and supplies; and concrete accessory material and labor.
  • The concrete work required coordination with Johnston Construction Company, CB&I Storage Tank Solutions, Berkeley County Public Service Water District, Dewberry Engineers Inc., concrete suppliers, testing agencies, concrete pumping services, equipment providers, and project stakeholders.

Electrical Services Division

  • Electrical Services Division, LLC performed electrical construction work for the Industrial Zone 2MGAL Elevated Water Storage Tank in Martinsburg, West Virginia.
  • The project included construction of a new 2,000,000-gallon composite elevated water storage tank as part of the Industrial Zone and Ridge Road Water Storage Tanks project for Berkeley County Public Service Water District.
  • ESD’s scope included conduit, wire, connections, electrical ductbank excavation, concrete encasement and rebar for electrical service ductbank, lighting, panel gear, power monitoring, surge protection, disconnects, phase monitor, heat tracing, lightning protection, testing, startup, and electrical closeout support.
  • Major electrical work included installation of lighting fixtures, conduit, boxes and devices, wire, switchgear, heat trace, lightning protection, electrical service ductbank, inspection, testing, startup, and two sets of six 6-inch conduits through the foundation.
  • The work required coordination with Johnston Construction Company, CB&I Storage Tank Solutions, Berkeley County Public Service Water District, Dewberry Engineers Inc., utility providers, electrical suppliers, testing services, tank manufacturer, and project stakeholders.