Harrington 500,000-Gallon Elevated Water Storage Tank and Well House

Harrington, Kent County, Delaware

LocationHarrington, Kent County, Delaware
MarketWater Storage and Tanks

NEW MUNICIPAL WELL, SUBMERSIBLE PUMP, CMU WELL HOUSE, WATER-TREATMENT FACILITY, ELEVATED WATER STORAGE TANK, PROCESS PIPING, ELECTRICAL SYSTEMS, CONTROLS, PAVING, AND SITE RESTORATION.

Johnston Construction Company

  • Johnston Construction Company completed the 500,000-Gallon Elevated Water Storage Tank and Well House project for the City of Harrington.
  • The project included construction of a new municipal well equipped with a submersible pump and motor.
  • JCC constructed a new concrete-masonry-unit well house and water-treatment facility to support the City’s expanded water-supply infrastructure.
  • The work included construction of a new 500,000-gallon spheroid welded-steel elevated water storage tank and the appurtenances required for a complete operating system.
  • JCC installed the associated process piping, valves, fittings, supports, water-service connections, electrical systems, controls, instrumentation, and facility equipment.

Concrete Services Division

  • Concrete Services Division, LLC completed the concrete work associated with the City of Harrington’s 500,000-Gallon Elevated Water Storage Tank and Well House project.
  • CSD furnished the labor, form materials, tools, equipment, finishing supplies, curing materials, and concrete accessories required for its assigned work.
  • The project included concrete construction for the elevated water-storage-tank foundation, well-house foundation, generator foundation, floor slabs, splash pads, pipe pads, door pads, sump pits, and associated structural features.
  • CSD completed footing, slab-on-grade, curved-wall, and column formwork required for the project’s concrete foundations and structures.
  • The work included concrete placement, floating, screeding, machine troweling, pointing, patching, curing, vapor-barrier installation, joint work, perimeter insulation, and pipe-pad construction.

Electrical Services Division

  • Electrical Services Division completed the electrical work associated with the City of Harrington’s 500,000-Gallon Elevated Water Storage Tank and Well House project.
  • ESD furnished and installed conduit, wiring, electrical connections, lighting, switches, receptacles, electrical service equipment, switchgear, panelboards, and surge-protection equipment.
  • The electrical work supported the new elevated water-storage tank, municipal well, well house, water-treatment facility, pumping equipment, and associated site improvements.
  • ESD installed underground electrical ductbanks and raceways serving the electrical service and the connections between the elevated tank and well house.
  • The work included four grounding rods at the base of the elevated tank for lightning-protection grounding.

Additional project details

  • The City of Harrington expanded its water supply and storage with a new municipal well, submersible pump, CMU well house and treatment facility, and a 500,000-gallon elevated storage tank.
  • JCC delivered the associated building, process, utility, electrical, and site work.