LocationEdinburg, Shenandoah County, Virginia
MarketWastewater Treatment Plants
CLARIFIER EFFLUENT PUMP STATION, FORCE MAIN, FLOW SPLITTER BOX, PROCESS PIPING, ELECTRICAL CONTROLS & SITE IMPROVEMENTS.
Johnston Construction Company
- Johnston Construction Company served as Prime Contractor for the wastewater treatment system improvements at George’s Chicken’s Edinburg, Virginia facility.
- Constructed a new Clarifier Effluent Pump Station and associated force main to support the plant’s wastewater treatment process.
- JCC coordinated installation of a simplex submersible pumping system designed for approximately 1,050 GPM at 95 feet TDH, utilizing a 58 HP, 480-volt, three-phase pump.
- Constructed a new Flow Splitter Box and associated piping to distribute wastewater flow among multiple treatment-process destinations.
- The splitter structure incorporated one 12-inch influent line and four 12-inch outlet lines serving Reactor No. 1, the anaerobic lagoon, anaerobic lagoon short-circuit flow, and the emergency storage lagoon.