Markets Served / Project Experience

George's Chicken Wastewater Treatment System Improvements

Edinburg, Shenandoah County, Virginia

LocationEdinburg, Shenandoah County, Virginia
MarketWastewater Treatment Plants

CLARIFIER EFFLUENT PUMP STATION, FORCE MAIN, FLOW SPLITTER BOX, PROCESS PIPING, ELECTRICAL CONTROLS & SITE IMPROVEMENTS.

Johnston Construction Company

  • Johnston Construction Company served as Prime Contractor for the wastewater treatment system improvements at George’s Chicken’s Edinburg, Virginia facility.
  • Constructed a new Clarifier Effluent Pump Station and associated force main to support the plant’s wastewater treatment process.
  • JCC coordinated installation of a simplex submersible pumping system designed for approximately 1,050 GPM at 95 feet TDH, utilizing a 58 HP, 480-volt, three-phase pump.
  • Constructed a new Flow Splitter Box and associated piping to distribute wastewater flow among multiple treatment-process destinations.
  • The splitter structure incorporated one 12-inch influent line and four 12-inch outlet lines serving Reactor No. 1, the anaerobic lagoon, anaerobic lagoon short-circuit flow, and the emergency storage lagoon.