LocationFront Royal, Warren County, Virginia
MarketPump Stations
INFLUENT LIFT STATION, PUMP, PIPING, CONCRETE, SPIRAL STAIR, DRAINAGE, AND SITE IMPROVEMENTS.
Johnston Construction Company and B & R Electrical Contractors
- Johnston Construction Company completed the Upgrade of Influent Pump Station at the Town of Front Royal Wastewater Treatment Plant.
- The project included improvements to the influent lift station, including pump replacement, piping, valves, concrete grout replacement, wet-well ventilation equipment, wet-well level sensors, spiral staircase replacement, electric manhole drainage, dewatering, excavation, grading, compaction, and restoration.
- JCC’s scope included construction coordination, sequencing, demolition, pump installation, pump foundation work, piping and valve replacement, removal of failed concrete grout, installation of new concrete grout layer, spiral staircase replacement, electric manhole drainage, site excavation, stormwater ditch grading, closeout, training, and turnover.
- The project required maintaining the influent pump station in operation during construction, with only one pump allowed to be shut down at a time.
- Each pump, foundation, valving, electrical components, and piping had to be removed and replaced in sequence before the next pump could be taken out of service.
- Johnston Construction Company and B & R Electrical Contractors, Inc. completed the Upgrade of Influent Pump Station at the Town of Front Royal Wastewater Treatment Plant.
- The project included influent lift station improvements, pump replacement, piping, valves, concrete grout replacement, wet-well ventilation equipment, wet-well level sensors, electrical equipment, controls, spiral staircase replacement, electric manhole drainage, and site restoration.
- JCC coordinated the overall project delivery, including sequencing, demolition, pump installation, foundation and grout work, piping, valves, spiral stair replacement, electric manhole drainage, dewatering, excavation, backfill, stormwater ditch grading, restoration, training, and closeout.
- BRE performed electrical, controls, VFD, motor control center, switchboard, pump wiring, wet-well level sensor, and startup support work.
- The work required maintaining the influent pump station in operation during construction, with only one pump allowed to be shut down at a time.
B & R Electrical Contractors
- B & R Electrical Contractors performed electrical work for the Front Royal Wastewater Treatment Plant Influent Pump Station Upgrade project in Front Royal, Virginia.
- The project included electrical support for upgrades to the influent lift station at the Town of Front Royal Wastewater Treatment Plant.
- BRE’s scope included conduit, wiring, electrical connections, electrical demolition, panelboard demolition, temporary power, VFD installation, switchboard installation, disconnect installation, motor starter installation, transducer conduit, electrical testing, arc flash support, startup, and closeout.
- Major electrical equipment included two 100 HP VFDs, two 75 HP VFDs, one 600A switchboard, two 200A disconnects, two 125A disconnects, and two fan disconnects / motor starters.
- BRE provided electrical demolition and make-safe work to support demolition of mechanical equipment by Johnston Construction Company.