Markets Served / Project Experience

Fort Detrick Water Treatment Plant Underdrain Filter Replacement

Fort Detrick, Frederick, Maryland

LocationFort Detrick, Frederick, Maryland
MarketWater Treatment Plants
DeliveryDesign-Build

DESIGN-BUILD REPLACEMENT OF FIVE WATER TREATMENT PLANT UNDERDRAIN FILTER SYSTEMS INCLUDING DESIGN, FIELD VERIFICATION, FILTER MEDIA REMOVAL AND STORAGE, DEMOLITION, FLOOR PREPARATION, UNDERDRAIN INSTALLATION, AIR-SUPPLY CONNECTIONS.

Johnston Construction Company

  • Johnston Construction Company performed design-build construction services for the replacement of five underdrain filter systems at the Fort Detrick Water Treatment Plant in Frederick, Maryland.
  • The project addressed Filter Cells 1A, 1B, 2, 3, and 4 within Building 1125, supporting the continued treatment and delivery of potable water at the active military installation.
  • JCC’s scope included development of the design required for replacement of the existing underdrain systems, field verification of dimensions and conditions, construction planning, demolition, installation, testing, and closeout.
  • The work included removal of the existing underdrain systems while carefully removing and storing the existing filter media for reuse during installation of the new systems.
  • JCC removed existing air-supply connections in a controlled manner to protect the existing air-distribution infrastructure and facilitate reconnection to the replacement underdrains.

Concrete Services Division

  • Concrete Services Division, LLC performed concrete, demolition, underdrain, and filter-media work for the replacement of five underdrain filter systems at the Fort Detrick Water Treatment Plant in Frederick, Maryland.
  • The project involved Filter Cells 1A, 1B, 2, 3, and 4 within Building 1125 and supported the continued operation of an active potable-water treatment facility.
  • CSD’s scope included concrete work, concrete demolition, concrete sawcutting, handling and disposal, Leopold underdrain-bottom work, filter-media installation, and filter-media removal through an eduction process.
  • The work included demolition, removal, and reinstallation of the existing filter underdrain systems in accordance with the approved project drawings, specifications, and manufacturer requirements.
  • CSD removed the existing filter media and supported its protected handling and storage so that the media could be reinstalled following completion of the underdrain work.

Additional project details

  • The design-build package replaced the underdrain systems in Filter Cells 1A, 1B, 2, 3, and 4 at Fort Detrick’s active water treatment plant.
  • The replacement addressed deteriorated underdrains while preserving potable-water production at the installation.