Markets Served / Project Experience

Federal Street 500,000-Gallon Elevated Water Storage Tank

Milton, Delaware

LocationMilton, Delaware
MarketWater Storage and Tanks

CIVIL, MECHANICAL, ELECTRICAL, AND INSTRUMENTATION CONSTRUCTION FOR NEW 500,000-GALLON ELEVATED WATER STORAGE TANK.

Johnston Construction Company

  • Johnston Construction Company performed civil, mechanical, electrical, and instrumentation construction work for the new Federal Street 500,000-gallon elevated water storage tank in Milton, Delaware.
  • The project included construction support for a new 500,000-gallon elevated water storage tank, associated site grading, foundation work, electrical work, piping work, and connection to the Town of Milton water system.
  • JCC’s scope included site preparation, erosion and sedimentation controls, site cut/fill, finish grading, seeding, temporary stone access road and laydown area, water main and force main piping, tank foundation construction, Rammed Aggregate Pier ground improvement coordination, dewatering, electrical conduit and wiring, electrical ductbank, lighting, instrumentation, testing, and closeout support.
  • Major work included mobilization, submittals, sediment control BMPs, traffic control signage, open-cut force main installation, under-structure piping, fire hydrant and piping installation, thrust blocks, resilient wedge gate valve installation, water main pressure testing and disinfection, tank foundation excavation, mud slab, stone sub-base, footer and wall forming, rebar, concrete placement, tank slab, splash pad, backfill, and interior ductile iron pipe.
  • The work required coordination with CB&I Storage Tank Solutions, Veolia, the Town of Milton, Pennoni Associates, utility providers, ground improvement subcontractors, electrical suppliers, inspection/testing agencies, and other project stakeholders.

Concrete Services Division

  • Concrete Services Division, LLC performed concrete forming, placement, finishing, curing, and accessory work for the new Federal Street 500,000-gallon elevated water storage tank in Milton, Delaware.
  • The project included construction of a new 500,000-gallon elevated water storage tank, associated site grading, foundation work, electrical work, piping work, and connection to the Town of Milton water system.
  • CSD’s scope included concrete work for the tank foundation, tank slab, and splash pad, including forming, concrete placement, finishing, curing, rebar dowel installation, sawcut joints, joint sealing, and concrete accessory work.
  • Major work included mobilization, form material rental, form lumber purchase, installation and stripping of forms, footing forming, slab-on-grade forming, curved wall forming, footing placement, slab placement, wall placement, float and screed work, trowel finishing, point and patch work, bagging, curing, and concrete accessory installation.
  • The concrete work required coordination with Johnston Construction Company, CB&I Storage Tank Solutions, the Town of Milton, Pennoni Associates, concrete suppliers, testing agencies, pumping services, equipment providers, and other project stakeholders.

Electrical Services Division

  • Electrical Services Division, LLC performed electrical construction work for the new Federal Street 500,000-gallon elevated water storage tank in Milton, Delaware.
  • The project included construction of a new 500,000-gallon elevated water storage tank, associated site grading, foundation work, electrical work, piping work, and connection to the Town of Milton water system.
  • ESD’s scope included conduit, wire, connections, lighting, switches, receptacles, mixer conduit, cathodic protection conduit, direct-burial electrical ductbank excavation, junction boxes, grounding, testing, startup, and record drawing support.
  • Major electrical work included installation of wall pack lighting, jelly jar fixtures, miscellaneous breakers in the existing panel, miscellaneous junction boxes, electrical ductbank work, grounding connection to the existing triad, inspection, testing, startup, and coordination of materials provided by others.
  • The work required coordination with Johnston Construction Company, CB&I Storage Tank Solutions, the Town of Milton, Pennoni Associates, electrical suppliers, testing services, equipment providers, utility providers, and project stakeholders.

Browse all project experience